Out of N155Billion cost for Kano-Abuja Road, N70Billiom has been released to Julius Berger. But sadly from Abuja to KD.which is 165km, only 10km work has been done. KD to Zaria is 75km but only 6km has been completed, while Zaria to Kano is 157km but less than 20km has been done. This was disclosed yesterday by the Chairman of House Committee on Works Hon Abubakar Bichi who led members of his committee on a tour of ongoing FG projects in North West Zone. I have said it before and I will repeat it again, Kano-Abuja Road will not be completed before 2023.